Project Introduction
SEC obtained this EPC project in November 2017, which included the foundation construction, wind turbine procurement and installation of two Vestas V105 wind turbines. This EPC project includes the preparation permission 、construction permission for 2 wind turbines, and overall construction (including five-year warranty operation and maintenance). The wind turbine will use Vestas V105 with a capacity of 3.6MW, which is the largest capacity onshore wind turbines. After the construction permit was obtained, the site foundation civil works started in May 2019, and the installation was completed and grid-connected operation was completed on Oct 28 of the same year.